UNIVERSITY DRIVE EXTENSION CONSTRUCTION TO IMPACT TRAFFIC

University Drive Extension
Thursday, April 6, 2017

The University Drive Extension from Park Avenue to just south of the Dairy Barn Access Road will close as construction begins on April 10 for a three-phase road construction project. Detours for the first two phases will be posted for both vehicular and pedestrian traffic to access University Drive Extension.

Phase one will be split into two time frames. The initial portion will take place between April 10 and May 7 and will allow the Campus Shuttle to maintain its normal route and minimize impacts to the annual Movin’ On concert scheduled for April 28.

On May 8, the second portion of phase one will extend the road closure from Park Avenue to just south of Services Road and close the intersection with the Dairy Barn Access Road. Construction includes new full-depth asphalt pavement with bike lanes on both sides, concrete curbs, lighting, underground utilities, traffic signal upgrades at Park Avenue, concrete sidewalks, and landscaping, with completion expected by early July. 

The University Drive Extension will remain closed for phase two, which includes the reconstruction of the Services Road intersection. The third and final phase, which includes top course paving, pavement markings and signage, will likely allow the reopening of the road with traffic controlled by flaggers.  

To provide an additional exit route, Big Hollow Road will be designated for exiting northbound traffic only to Fox Hollow Road on weekdays from 3:30 p.m. to 5:30 p.m. Click on the Big Hollow Exit Route Google Map to view a map of the alternate route.

Weather-permitting, the project is expected to be completed by July 28.